From the Streetscape Master Plan draft:
IMPLEMENTATION PRIORITIES
The Round Hill Streetscape Master Plan Steering Committee recommended a
series of priority projects as a focus for the Town’s initial
implementation efforts. These “Top Five” priority projects were
considered the as the most urgent and important tasks to be undertaken,
both for improving safety and enhancing the appearance of the
streetscape in the Town. For each priority project, the Steering
Committee identified key resource people on the committee for
coordinating the projects and primary “next steps” to begin
implementation.
“TOP FIVE” PRIORITY PROJECTS:
1. STORMWATER MANAGEMENT PLAN
Issues
• The Town Council has already issued Requests for Proposals for firms
to conduct a comprehensive Stormwater management study of the Town.
• The Town Council is working on developing funding for both the
Stormwater management Study and for a Right of Way survey of Route 719,
which will be needed for both the Stormwater Management Study and for
future streetscape improvements.
Actions/Next Steps
• Continue to work with the Council on developing the Study and
implementing its recommendations.
• Ensure that future Stormwater Management improvements are compatible
with the Streetscape Master Plan
2. FRANKLIN PARK TRAIL
Issues
• A Subcommittee of the Steering Committee is currently working on
developing final recommendations for the portion of the Franklin Park
Trail in the Town.
• The subcommittee will present its final recommendations for detailed
design of sidewalks, crosswalks, street lighting and other improvements
to the Town Council and the County
Actions/Next Steps
• Continue to finalize detailed design recommendations
• Work with the County to ensure compatibility with the subcommittee
recommendations and the overall Streetscape Master Plan
GATEWAY SIGNS
Issues
• All four Town gateway signs have been funded and designed and one has
been constructed.
Actions/Next Steps
• Identify key properties and residents at gateway locations for
assistance and review of the locations for installing each sign
• Identify tasks and schedule for each sign installation
• Ensure compatibility with the overall Streetscape Master Plan
recommendations at each location
ROUTE 719 NORTH
Issues
• The County has received a rezoning application for residential
development by Richmond American on the key gateway property at the
north gateway of the Town.
• The proposal shows a significant realignment of Route 719, which
would alter traffic patterns at the gateway
• There are prior agreements with the developers of Greenwood Commons
and The Villages at Round Hill to extend trails along Route 719 and in
the adjacent stream valley.
Actions/Next Steps
• Work with the Town Council, the County and the Richmond American
applicants to address gateway design issues
• Ensure development of the overall trail network and sidewalk
extensions proposed in the area
• Begin a detailed study of the traffic calming and pedestrian safety
issues along this stretch of Rt. 719 and ensure that they are
compatible with the Streetscape Master Plan
WESTERN GATEWAY
Issues
• The County and Town have received an application for residential
on the key gateway “Webster” property at the west end of Loudoun Street
Actions/Next Steps
• Work with the Town Council, the County and the Webster property
applicants to address gateway design issues and ensure compatibility
with the Streetscape Master Plan