From the Streetscape Master Plan draft:
The following recommendations outline a series of specific projects
and improvements tailored to each of the districts identified above.
The recommendations are not an exhaustive list but represent the key
priorities identified by consensus as part of the Master Plan process.
NORTH MAIN STREET
Fire Station
Work with owners to develop improvement plans that reduce curb
cuts, formalize parking areas and integrate with Streetscape plan
Post Office
Work with owners to develop improvement plans that reduce curb
cuts, formalize parking areas and integrate with Streetscape plan
On-Street Parking West Side
Provide parallel on-street parking along west side to formalize
spaces currently used for informal parking in this area
Integrate parking areas with roadway and streetscape design
Existing Sidewalk East Side
Maintain current sidewalk on the east side
Construct replacement sidewalks to match other new Town sidewalks
over time
On-Street Parking East Side
Provide parallel on-street parking along east side to formalize
spaces for current informal parking in this area
Integrate parking areas with roadway and streetscape design
Existing Sidewalk West Side
Maintain current sidewalk on the west side
Construct replacement sidewalks to match other new Town sidewalks
over time
New Sidewalk & Crosswalk
Extend new sidewalk on west side to intersection with High Street
Consider installing traffic calming measures such as stop sign or
speed table at the Greenwood Commons Drive intersection (See Detailed
Recommendations section)
Extend sidewalks on west side of Main Street to future Route 719
trail to Evening Star Drive
Future Trail & Sidewalk Connections
Work with Route 719 properties to develop a trail section along
Route 719 on the west side north to Evening Star Drive
Northern Gateway
Develop traffic calming strategy along northern gateway to manage
traffic speed entering Town design (See
Detailed Recommendations